| gsd_state_version | milestone | milestone_name | status | stopped_at | last_updated | last_activity | progress | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1.0 | v1.3 | Web Chat Interface | roadmap_defined | Activated v1.3 from milestone queue — ready to plan Phase 21 | 2026-04-01T14:00:00.000Z | 2026-04-01 |
|
Project State
Project Reference
See: .planning/PROJECT.md (updated 2026-03-30)
Core value: Fresh onboard asks for ONE thing (root directory), auto-creates PM + Engineer, drops you in dashboard — no corporate language anywhere. Current focus: v1.3 Web Chat Interface — ready to plan Phase 21
Current Position
Phase: 21 of 26 (Chat Foundation) Plan: — (not yet planned) Status: Ready to plan Last activity: 2026-04-01 — upstream rebase verified (0 behind, build OK)
Progress: [░░░░░░░░░░] 0%
Upstream Rebase Log
| Date | Commits Behind | Conflicts | Build | Notes |
|---|---|---|---|---|
| 2026-04-01 | 0 | 0 | OK | Already rebased from 120+ commits session; upstream hasn't moved |
Performance Metrics
Velocity:
- Total plans completed: 0
- Average duration: -
- Total execution time: 0 hours
By Phase:
| Phase | Plans | Total | Avg/Plan |
|---|---|---|---|
| - | - | - | - |
Recent Trend:
- Last 5 plans: none yet
- Trend: -
Updated after each plan completion | Phase 01-foundation P01 | 2 | 2 tasks | 7 files |
Accumulated Context
Decisions
Decisions are logged in PROJECT.md Key Decisions table. Recent decisions affecting current work:
- Roadmap: Company → Workspace (not Project) to avoid collision with existing Project entity
- Roadmap: Display-only renames — all code identifiers, DB schema, routes, env vars unchanged
- Roadmap: Branding package (
packages/branding/) as single string mutation surface - Roadmap: Vite alias redirects OnboardingWizard import to Nexus-owned replacement (Phase 4)
- Roadmap:
~/.nexuspointer file with read-both-paths fallback for migration safety (Phase 2) - [Phase 01-foundation]: Keep @paperclipai/branding package name for upstream sync compatibility
- [Phase 01-foundation]: Use as const for VOCAB to enable TypeScript literal type inference on all values
- [Phase 01-foundation]: Hook source tracked in scripts/nexus-commit-msg-hook.sh for post-clone reinstallation
- [Phase 01-foundation]: rerere.autoupdate=true so resolved conflicts are auto-staged during future rebases
Pending Todos
None yet.
Blockers/Concerns
- Phase 4:
POST /api/companiesrequired fields not fully documented — readserver/src/routes/companies.tsbefore implementing new wizard - Phase 3: Exact count of test files asserting on old display strings unknown — grep audit needed as first step
Session Continuity
Last session: 2026-03-30T20:37:04.573Z Stopped at: Completed 01-foundation/01-02-PLAN.md Resume file: None