Milestone v1.3 — Audit Report
Audited: 2026-04-02 Status: tech_debt (all requirements checked, 3 integration gaps, accumulated debt)
Requirements Coverage
Score: 63/63 requirements checked in REQUIREMENTS.md
All requirement IDs across phases 21-26 are marked [x] complete.
Phase Verification Summary
| Phase | Name | Status | Score |
|---|---|---|---|
| 21 | Chat Foundation | passed | 13/13 |
| 22 | Agent Streaming | passed | 28/28 |
| 23 | Brainstormer Flow | human_needed | 13/15 |
| 24 | Search, History & Branching | gaps_found | 3/4 |
| 25 | File System | human_needed | 15/15 |
| 26 | PWA & Performance | gaps_found | 8/10 |
Cross-Phase Integration Issues
1. Push notifications never fire (PWA-06)
sendPushToAll in pushService.ts is defined but never called from any server-side event handler. The SSE streaming endpoint in chat.ts completes without dispatching push. Infrastructure is complete; trigger is missing.
2. Mobile offline queue not wired (PWA-01 partial)
MobileChatView.tsx does not use useOfflineQueue or useOnlineStatus. Its handleSend makes direct network calls with no offline guard. The OfflineBanner, InstallPromptBanner, and NotificationPermissionPrompt are also absent from the mobile layout.
3. New conversation streaming broken (CHAT-01 Path 1)
After creating a new conversation, ChatPanel and MobileChatView set activeConversationId but never call startStream. The first message in any new conversation gets no agent response until the user sends a second message.
Tech Debt Summary
Total: 8 items across 4 phases
- Phase 23: 2 human verification items pending
- Phase 24: Search does not index file attachment names
- Phase 25: 8 human verification items pending (drag-drop, paste, voice, git)
- Phase 26: vendor-react chunk empty, install/notification prompts missing on mobile
Nyquist Validation Coverage
| Phase | VALIDATION.md | Compliant |
|---|---|---|
| 21 | exists | true |
| 22 | exists | true |
| 23 | exists | false (partial) |
| 24 | missing | — |
| 25 | missing | — |
| 26 | exists | false (partial) |
Recommendation
All 63 requirements are formally checked. The 3 integration gaps are real wiring bugs but are each a 5-15 line fix. The tech debt is manageable. Milestone can proceed to completion with these items tracked.